Contract
No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-356/2009, Further
Evironmental permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009
and fep-05/356/2009 Quarterly Environmental Monitoring
and Audit Report
- December 2012 to FeBruary 2013 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
March 2013 |
2.2 Scope
of the Project and Site Description
2.3 Division of the Project
Responsibility
2.4 Project Organization and Contact
Personnel
2.5 Principal Work and Activities
4.2. Real Time Noise Monitoring Results
5.2. Real-time Noise Monitoring
5.6. Review
of the Reasons for and the Implications of Non-compliance
5.7. Summary
of action taken in the event of and follow-up on non-compliance
6. Complaints, Notification
of Summons and Prosecution
7. Cumulative Construction
Impact due to the Concurrent Projects.
lIST
OF TABLES
Table I Principal Work Activities for Contract no.
HY/2009/11
Table II Principal Work Activities for Contract no.
HK/2009/01
Table III Principal Work Activities for Contract no.
HK/2009/02
Table IV Principal Work Activities for Contract no.
HY/2009/15
Table V Principal Work Activities for Contract no.
HK/2010/06
Table
2.1 Schedule 2
Designated Projects under this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 2.4 Principal Work Activities for Contract no.
HY/2009/11
Table 2.5 Principal Work Activities for Contract no.
HK/2009/01
Table 2.6 Principal Work Activities for Contract no.
HK/2009/02
Table 2.7 Principal Work Activities for Contract no.
HY/2009/15
Table 2.8 Principal Work Activities for Contract no.
HK/2010/06
Table 3.1 Noise
Monitoring Stations
Table 3.2 Real
Time Noise Monitoring Station
Table 3.3 Air
Monitoring Stations
Table 3.4 Marine
Water Quality Stations for Water Quality Monitoring
Table 3.5 Marine Water Quality Monitoring
Frequency and Parameters
Table 3.6 Marine Water Quality Stations for
Enhanced Water Quality Monitoring
Table 3.7 Marine Water Quality Stations for Additional
DO Monitoring
Table 4.1 Noise Monitoring Stations for Contract
no. HY/2009/11
Table 4.2 Noise Monitoring Station for Contract
nos. HK/2009/01 and HK/2009/02
Table 4.3 Noise Monitoring Station for Contract
nos. HY/2009/15
Table 4.4 Real Time Noise Monitoring Station for
Contract no. HY/2009/11 and HY/2009/19
Table 4.6 Real Time Noise Monitoring Station for
Contract no. HY/2009/11 andHY/2009/19
Table 4.7 Air Monitoring Stations for Contract
no. HY/2009/11
Table 4.8 Air
Monitoring Stations for Contract no. HK/2009/01
Table 4.9
Air Monitoring Stations for Contract
no. HY/2009/19
Table 4.10 Air Monitoring Station for Contract no. HY/2009/15
Table 4.11 Air Monitoring Station for Contract no.
HY/2009/19
Table 4.12 Water Monitoring Stations for Contract
no. HY/2009/11
Table 4.13 Water Monitoring Stations for Contract
no. HK/2009/01
Table 4.14 Water Monitoring Stations for Contract
no. HK/2009/02
Table 4.15 Water Monitoring Stations for Contract
no. HK/2010/06
Table 4.16 Water Monitoring Stations for Contract
no. HY/2009/15
Table 4.16a Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting period
Table 4.18 Summary
of Water Quality Monitoring Exceedances in Reporting period
Table 4.19 Details
of Waste Disposal for Contract no. HY/2009/11
Table 4.20 Details
of Waste Disposal for Contract no. HK/2009/01
Table 4.21 Details
of Waste Disposal for Contract no. HK/2009/02
Table 4.22 Details
of Waste Disposal for Contract no. HY/2009/15
Table 5.1 Summary of Water Quality Monitoring Exceedances in
Reporting period
Table 5.1a Summary of Enhanced Dissolved Oxygen Monitoring
Exceedances in Reporting period
Table 6.1 Cumulative Statistics on Complaints
Table 6.2 Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 3.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix 2.1 Environmental
Mitigation Implementation Schedule
Appendix 3.1 Action
and Limit Level
Appendix 4.1 Noise
Monitoring Graphical Presentations
Appendix 4.2 Air
Quality Monitoring Graphical Presentations
Appendix 4.3 Water
Quality Monitoring Graphical Presentations
Appenidx 4.3a Additional Dissolved Oxygen
Monitoring Results
Appendix
4.4 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 5.1 Event
Action Plans
Appendix 6.1 Complaint
Log
Appendix 7.1 Construction Programme of Individual Contracts
Construction Activities for the
Reported Period
Table I Principal Work Activities for Contract
no. HK/2009/01
December 2012 |
January 2013 |
February 2013 |
Marine Works (at Wan Chai) Rockfilling
of HKCEC3E (East of HKCEC) between CH290 and CH385 Lateral
supporting temporary pipe pile wall including grouting and tie back
installation works Removal of
existing seawall and rock armour at Dredging
works for Type 2 sediment beneath Installation
of precast seawall blocks for caisson and box culvert (Bay 10) installation Fabrication
of 3 nos. precast concrete caisson seawall, 1 no. precast concrete box
culvert (namely Bay10) and 2 nos. precast discharge outfall in precasting
yard at Cross-Harbour Watermains Installation (CHA
& CHB) and Marine Works (at TST) Rockfilling
and rock protection to cross-harbour watermains Thrust
block construction for A18B18 Reinstatement
works for the TST landfall was temporary suspended and the site area was
handed over to LCSD Construction
of transformer rectifier at new reclaimed area Fresh Watermains, Cooling Watermains and Salt
Watermains (On Land) Mainlaying
works at Zone B6-1, B6-3, B6-5, B3-1, A1-1, A1-2, A1-4, A1-2A & A1-3A,
A2-3D, A3-2A, A3-4A, A3-5A, A3-3C, C1-6 and Run-out of Renaissance Hotel Mainlaying
works and partially reinstatement in Zone A1-1 & A1-2 Mainlaying
works and subsequent reinstatement in Zone A2-3D (Stage 1), A3-2A &
Heading No. 1 and A3-4B Mainlaying
works at Zone A3-4A, A3-5A and A3-3C Mainlaying
and chamber construction works at the traffic island near junction of Mainlaying
works in Zone C1-6 of Mainlaying
works for proposed sewerage system in Zone B6-1, B6-3 (previously named
B1-5A) and B6-5 (previously named B2-1) Final
cleaning, CCTV inspection and pressure test for the 9 nos. cooling watermains
23 out of 27 sections of cooling mains pipeline has been satisfied the
pressure test. E&M Full
commissioning test for Cooling Water Pumping Station P1 Site test
for all E&M equipment and facilities in Cooling Water Pumping Station P5
Preparation works including testing and
commissioning of all E&M equipment, BMS system and facilities in Cooling
Water Pumping Station P3 and P4 |
Marine Works (at Wan Chai) Rockfilling
of HKCEC3E (East of HKCEC) between CH290 and CH385 Dredging
works for Type 2 sediment near Wan Chai West Ferry Pier Rockfilling
at the southern part of HKCEC3E (East of HKCEC) between CH290 and CH385 for
subsequent open channel construction Installation
of precast seawall blocks for caisson and box culvert (Bay 10) installation Installation
of precast units including caisson seawalls, box culvert (namely Bay10) and
discharge outfall was commenced and substantially completed Cross-Harbour Watermains Installation (CHA
& CHB) and Marine Works (at TST) Rockfilling
and rock protection to cross-harbour watermains Reinstatement
works including seawall coping, gully, drawpit and tree transplantation for
the TST landfall was resumed. Construction
of transformer rectifier at new reclaimed area was completed in reporting
month and its cabling work Fresh Watermains, Cooling Watermains and Salt
Watermains (On Land) Mainlaying
works at Zone B6-1, B6-3, B6-5, A1-2A & A1-3A, A2-3D (Stage 2), A3-3B,
A3-4A, A3-5A, A3-3C and C1-4. Mainlaying
works and substantially reinstatements in combined Zone A1-1 & A1-2, Zone
A1-4 and Run-out of Renaissance Hotel. Mainlaying
works at Zone A1-3 (CHWM). Mainlaying
works at Zone A1-2 (CHWM), Zone A2-3D (Stage 2) and A3-3B. Mainlaying
works at Zone A3-4A and A3-5A. Mainlaying
works at Zone A3-3C. Mainlaying
and chamber construction works at the traffic island near junction of The
preparation works (including exposure of installed gate valve and repair of
gate valve) at Mainlaying
works at Zone C1-4. Mainlaying
works for proposed sewerage system in Zone B6-1, B6-3 (previously named
B1-5A) and B6-5 (previously named B2-1) Final
cleaning, CCTV inspection and pressure test for the 9 nos. cooling watermains
25 out of 27 sections of cooling mains pipeline has been satisfied the
pressure test. Tunnel Works Backfilling
works on top of SCL protection works. Pre-bored
H piling works for the proposed CWB and altogether 10 nos. and 9 nos. of
pre-bored H piles. Pre-drilling
works for CWB (Stage 2). Ground
treatment works for proposed CWB diaphragm wall. Plant
Mobilization for diaphragm wall construction works at Stage 2. E&M Full
commissioning test for Cooling Water Pumping Station P1
Site test for all E&M equipment and
facilities in Cooling Water Pumping Station P5 |
Marine Works (at Wan Chai) Rockfilling
at the northern part of HKCEC3E (East of HKCEC) between CH290 and CH385. Rockfilling
at the southern part of HKCEC3E (East of HKCEC) between CH290 and CH385 for
subsequent open channel construction. Installation
of precast block seawall (Type 1, 2 & 3). Construction
of mass concrete coping for new seawall. Cross-Harbour Watermains Installation (CHA
& CHB) and Marine Works (at TST) Rockfilling
and rock protection to cross-harbour watermains. Reinstatement
works including seawall coping, gully, drawpit and tree transplantation for
the TST landfall. CCTV
inspection for cross-harbour water main (including CHA, CHB, CHE & CHF). Fresh Watermains, Cooling Watermains and Salt
Watermains (On Land) Mainlaying
works at Zone B6-1, B6-3, B6-5, A1-2A & A1-3A, A3-3C and C1-2 . Mainlaying
works and substantially reinstatements in Zone A1-2, A2-3D (Stage 2), C1-4
and A3-4A. Grouting,
pipe connection and reinstatement works in combined Zone A1-2A & A1-3A. Grouting,
pipe connection and reinstatement works in Zone A1-3B. Mainlaying
works and substantially reinstatements in Zone A3-5A, A3-3B and footpath of Preparation
works at Zone A3-3C for subsequent connection works. The
preparation works (including exposure of installed gate valve and repair of
butterfly valve) at The
preparation works (including exposure of installed gate valve and repair of
gate valve) at Mainlaying
works at Zone C1-2. Mainlaying
works and coring works at external wall of seawater pumping stations for
proposed sewerage system in Zone B6-1. Mainlaying
works and substantially reinstatements in Zone B6-3 (previously named B1-5A)
and B6-5 (previously named B2-1). Final
cleaning, CCTV inspection and pressure test for the 9 nos. cooling
watermains. CCTV
inspection for cross-harbour watermains (land pipe at Wan Chai). Pressure
test for cross harbour watermains (whole length of land pipes in Wan Chai). Trench
excavation for HEC and PCCW cabling works connected to the proposed
transformer rectifier at new reclaimed area. Tunnel Works Backfilling
works on top of SCL protection works. Pre-bored
H piling works for the proposed CWB stage 1b Pre-drilling
works for CWB (Stage 2). Diaphragm
wall construction works at Stage 2. Removal of
remaining guide wall along E & M Full
commissioning test for Cooling Water Pumping Station P1. Site test
for all E&M equipment and facilities in Cooling Water Pumping Station P5. Initial
commissioning test for Cooling Water Pumping Station P5. |
Table II Principal Work Activities
for Contract no. HK/2009/02
December 2012 |
January 2013 |
February 2013 |
Concreting
the slab with hanger wall for planting area (+13.55mPD) between G.L.3-6/B-C
& E-F on Observation Deck Level (+14.65mPD) Concreting
the base slab and wall of sprinkler water tank machine room and the slab of
Machine Room Installation
of concrete block wall for store room 1 and room 2 on Level 1 Erecting
the wall stem formwork for caisson seawall precast unit 2X on flat-top barge Modification
work of PTI at Modification
work of bus station at Breaking
up the existing covered walkway footing at Rectification
works at bending block of cooling mains E&M
works and ABWFs installation at WSD Salt Water Pumping Station Drilling
hole and installation of pipe bracket for aeration and chlorination pipe
inside salt water intake Concreting
of the structure at salt water intake Steel
fixing of the shaft of Bay 2a in salt water intake seaside cofferdam Breaking
the existing concrete road slab for DN800 salt water mains at Ex-pet garden
near gate 1 Installation
the shoring to trial pit of the permanent connection point to existing DN 600
water main at Installation
of precast concrete short pipe extended from the existing 1800 drainage at
Box Culvert N landside |
Modification
work of PTI at Modification
work of bus station at Breaking
up the existing covered walkway footing at Concreting
the retaining wall base slab of Bay1, Bay 2 and Bay 5 at Rectification
works at bending block of cooling mains. Backfilling
at the conjunction between Tonnochy road and E&M
works and ABWFs installation at WSD Salt Water Pumping Station. Concreting
infill mass concrete at both sides and concreting 1m width x 300mm high mass
for cover M.J. at Bay 9 to Bay 11 in salt water intake landside cofferdam. Backfilling
grade 200mm rock material in the trench at Bay 6 to Bay 8 in salt water
intake landside cofferdam. Drilling
hole and installation of pipe bracket for aeration and chlorination pipe
inside salt water intake The shafts
of Intake chamber No.1 and No.2 for Bay 2A in salt water intake seaside
cofferdam were casted the 2nd layer of the horizontal struts. Placing
concrete for bend blocks btw CHS8A 150-165 at Ex-pet garden near new Gate
No.2. Installation
the shoring to trial pit of the permanent connection point to existing DN 600
water main at Saw
cutting of southern diaphragm wall for the connection between existing
drainage and Bay 1 of box culvert N1. Laying
1800mm dia. concrete pipe for the connection between existing drainage and
Bay 1 of box culvert N1. Erecting
formwork for concrete surround for concrete pipe. Concreting
of columns (total 6nos.) from M/F (+11.15mPD) to Observation Deck Level
(+14.65mPD) and Slab with beam between G.L.1-3/B-F on Level 2 (+7.65mPD). Concreting
of columns (total 9nos.) from Level 2 (+7.65mPD) to Observation Deck Level
(+14.65mPD). Concreting
of portion 2 for column C2C from +11.65mPD to +13.90mPD up to Observation
Deck Level (+14.65mPD). Concreting
of portion 1 for column C2E from +7.65mPD to +11.65mPD up to Observation Deck
Level (+14.65mPD). Steel
fixing and Formwork erection to Observation Deck Level at from GL 3-8 &
9-15. Installation
of concrete block wall for store room 1 and room 2 on Level 1. Placing
concrete of the final portion for precast scission seawall 2X. |
Modification
work of PTI at Modification
of existing covered walkway along Pressure
tests and the necessary rectification works for the installed cooling
watermains. Backfilling
for trench at the junction between E&M
works and their T&C in Cooling Water Pumping Stations P7, P8 and P9. Wet Tests
at WSD Salt Water Pumping Station. Backfilling
grade Drilling
hole and installation of pipe bracket for aeration and chlorination pipe
inside salt water intake Diver work
for excavation down to formation level at Bay 1B in salt water intake seaside
cofferdam. Mainlaying
works for DN800 salt watermains (CHS Works for
the Outfall B had been and the dye test. Switching
over works for sewage to WCE PTW. RC
structures for the proposed Ferry Pier. Construction
of eastern concrete staircase to Observation Deck Level. Concreting
of base slab with stem wall for PT2 & PT3 at Level 1 (under +4.15mPD). Installation
of concrete block wall for store room 1 and store room 2 on Level 1. Application
of protective coating to proposed precast caisson seawall 2X Eastern
Bulkhead Wall, Panel BHP3, BHP7 and BHP9 were cast (3 out of 13 panels) and
excavation for Panel BHP5. |
Table III
Principal Work
Activities for Contract no. HY/2009/15
December 2012 |
January 2013 |
February 2013 |
TZ1 and
TS2 reclamation works Formation
of temporary seawall at TS2 |
TZ1 and
TS2 reclamation works Formation
of temporary seawall at TS2 |
Removal of
eastern breakwater of CBTS |
Table IV Principal
Work Activities for Contract no. HK/2010/06
December 2012 |
January 2013 |
February 2013 |
Sheet
piling Platform
Disassembly Bored pile
casing cutting Grouting |
Disassembly
of staging platform Pile case
cutting Sheet pile
installation Dredging Construction
of pre-cast unit in mainland |
Pile Head
Breaking Pile
Casing Cutting Sheet
Piling Works Dredging Utility
Diversion Works Precast
Unit Box Construction (mainland |
Table
V
Principal Work
Activities for Contract no. HY/2009/19
December 2012 |
January 2013 |
February 2013 |
Marine
bored piling Construction
works for Box Culvert T Construction
of 1500f drainage
pipe |
Road works
at Bored
piling (Land) Pre-drilling
works for bored pile and Diaphragm wall D-wall Construction
(North & South Section) Guide wall
construction for D-wall / Barrette at North side Construction
works for Box Culvert T1 Marine
Piling Construct
ion of socket-H pile Construction
works for Culvert U1 Construction
of Pile cap & column (Land) Dismantling
of marine platform Demolition
of parapet at IEC Link Construction
of Pile caps & columns (Marine) Cut &
Cover Tunnel sheet piling works and installation of King Post Construction
of dewatering well for Cut & Cover Tunnel |
Road works
at Bored
piling (Land) Pre-drilling
works for bored pile and Diaphragm wall D-wall Construction
(North & South Section) Guide wall
construction for D-wall / Barrette at North side Construction
works for Box Culvert T1 Marine
Piling Construct
ion of socket-H pile Construction
works for Culvert U1 Construction
of Pile cap & column (Land) Dismantling
of marine platform Demolition
of parapet at IEC Link Construction
of Pile caps & columns (Marine) Cut &
Cover Tunnel sheet piling works and installation of King Post D8-D9
Gantry Fabrication for precast segment will continue Construction
of dewatering well for Cut & Cover Tunnel ELS for
Cut & Cover Tunnel |
Noise Monitoring
Real-time Noise Monitoring
Air Quality Monitoring
CMA2a: from 13 December 2012 to 14 December 2012
CMA3a: from 22 December 2012 to 24 December 2012
from 26 Jan 2013 to 28 Jan 2013
CMA6a: from 1 December 2012 to 3 December 2012
CMA5a: from 26 Feb 2013 to 27 Feb 2013
Water Quality Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-356/2009 and Further Environmental
permit nos. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the Environmental Monitoring and
Audit (EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.4 of EM&A Manual and “Environmental
Monitoring and Audit Requirements” under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
during the period from December 2012 to February 2013
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements – summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
The
Project is located mainly in Wan Chai North,
2.2.2.
The
study area encompasses existing developments along the Wan Chai,
2.2.3.
The scope of the Project comprises:
·
Land formation for key transport infrastructure and
facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for
connection to the Trunk Road and for through traffic from Central to Wan Chai and
Causeway Bay. The land formed for the above transport infrastructure will provide
opportunities for the development of an attractive waterfront promenade for the
enjoyment of the public
·
Reprovisioning / protection of the existing
facilities and structures affected by the land formation works mentioned above
·
Extension, modification, reprovisioning or
protection of existing storm water drainage outfalls, sewerage outfalls and
watermains affected by the revised land use and land formation works mentioned
above
·
Upgrading of hinterland storm water drainage system
and sewerage system, which would be rendered insufficient by the land formation
works mentioned above
·
Provision of the ground level roads, flyovers,
footbridges, necessary transport facilities and the associated utility services
·
Construction of the new waterfront promenade, landscape
works and the associated utility services
·
The Trunk Road (i.e. CWB) within the study area and
the associated slip roads for connection to the Trunk Road.
2.2.4.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule
2 Designated Projects under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits (FEP) such that the impact monitoring stations are sub-divided
accordingly to facilitate the implementation of EM&A programme and to
streamline the EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The
details of individual contracts are summarized in Table2.2.
Table
2.2 Details of Individual Contracts under
the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II – Central –Wanchai Bypass at |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central – Wan Chai Bypass – North
Point Reclamation |
DP3 |
17 March 2010 (Under applicationof surrender) |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel ( |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact
Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer’s Representative for
WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint
Venture Board Representative |
|
2162 9909 |
2587 1878 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Deputy Site
Agent |
Mr Andy Yu |
9648 4896 |
|||
Sub-Agent |
Mr Terry
Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 3008 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy
Mak |
9103 2370 |
|||
Environmental
Supervisor |
Kwong Weng
Kit |
6253 3356 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Deputy Project
Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658 3000 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
P J Fan |
3557 6368 |
2566 2192 |
||
|
|
Contractor’s Representative |
Mr. David Lau |
3557 6368 |
2566 2192 |
|
|
Head of Construction Manager |
Roger Cheung |
3557 6371 |
2566 2192 |
|
|
Senior Construction Manager |
Gene Cheung |
3557 6395 |
2566 2192 |
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|
||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental Officer |
Mr. Lee Wai Man |
9481 6024 |
|||
Environmental
Supervisor |
|
9735 9200 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
34652888 |
34652899 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
During
this reporting period, the principal work activities for Contract no.
HK/2009/01 are summarized in Table 2.4.
Table
2.4 Principal Work Activities for
Contract no. HK/2009/01
December
2012 |
January 2013 |
February
2013 |
Marine
Works (at Wan Chai) Rockfilling
of HKCEC3E (East of HKCEC) between CH290 and CH385 Lateral
supporting temporary pipe pile wall including grouting and tie back
installation works Removal of
existing seawall and rock armour at Dredging
works for Type 2 sediment beneath Installation
of precast seawall blocks for caisson and box culvert (Bay 10) installation Fabrication
of 3 nos. precast concrete caisson seawall, 1 no. precast concrete box
culvert (namely Bay10) and 2 nos. precast discharge outfall in precasting
yard at Cross-Harbour
Watermains Installation (CHA & CHB) and Marine Works (at TST) Rockfilling
and rock protection to cross-harbour watermains Thrust
block construction for A18B18 Reinstatement
works for the TST landfall was temporary suspended and the site area was
handed over to LCSD Construction
of transformer rectifier at new reclaimed area Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land) Mainlaying
works at Zone B6-1, B6-3, B6-5, B3-1, A1-1, A1-2, A1-4, A1-2A & A1-3A,
A2-3D, A3-2A, A3-4A, A3-5A, A3-3C, C1-6 and Run-out of Renaissance Hotel Mainlaying
works and partially reinstatement in Zone A1-1 & A1-2 Mainlaying
works and subsequent reinstatement in Zone A2-3D (Stage 1), A3-2A &
Heading No. 1 and A3-4B Mainlaying
works at Zone A3-4A, A3-5A and A3-3C Mainlaying
and chamber construction works at the traffic island near junction of Mainlaying
works in Zone C1-6 of Mainlaying
works for proposed sewerage system in Zone B6-1, B6-3 (previously named
B1-5A) and B6-5 (previously named B2-1) Final
cleaning, CCTV inspection and pressure test for the 9 nos. cooling watermains
23 out of 27 sections of cooling mains pipeline has been satisfied the
pressure test. E&M Full
commissioning test for Cooling Water Pumping Station P1 Site test
for all E&M equipment and facilities in Cooling Water Pumping Station P5 Preparation
works including testing and commissioning of all E&M equipment, BMS
system and facilities in Cooling Water Pumping Station P3 and P4 |
Marine
Works (at Wan Chai) Rockfilling
of HKCEC3E (East of HKCEC) between CH290 and CH385 Dredging
works for Type 2 sediment near Wan Chai West Ferry Pier Rockfilling
at the southern part of HKCEC3E (East of HKCEC) between CH290 and CH385 for
subsequent open channel construction Installation
of precast seawall blocks for caisson and box culvert (Bay 10) installation Installation
of precast units including caisson seawalls, box culvert (namely Bay10) and
discharge outfall was commenced and substantially completed Cross-Harbour
Watermains Installation (CHA & CHB) and Marine Works (at TST) Rockfilling
and rock protection to cross-harbour watermains Reinstatement
works including seawall coping, gully, drawpit and tree transplantation for
the TST landfall
was resumed. Construction
of transformer rectifier at new reclaimed area was completed in reporting
month and its cabling work Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land) Mainlaying
works at Zone B6-1, B6-3, B6-5, A1-2A & A1-3A, A2-3D (Stage 2), A3-3B,
A3-4A, A3-5A, A3-3C and C1-4. Mainlaying
works and substantially reinstatements in combined Zone A1-1 & A1-2, Zone
A1-4 and Run-out of Renaissance Hotel. Mainlaying
works at Zone A1-3 (CHWM). Mainlaying
works at Zone A1-2 (CHWM), Zone A2-3D (Stage 2) and A3-3B. Mainlaying
works at Zone A3-4A and A3-5A. Mainlaying
works at Zone A3-3C. Mainlaying
and chamber construction works at the traffic island near junction of The
preparation works (including exposure of installed gate valve and repair of
gate valve) at Mainlaying
works at Zone C1-4. Mainlaying
works for proposed sewerage system in Zone B6-1, B6-3 (previously named
B1-5A) and B6-5 (previously named B2-1) Final
cleaning, CCTV inspection and pressure test for the 9 nos. cooling watermains
25 out of 27 sections of cooling mains pipeline has been satisfied the
pressure test. Tunnel
Works Backfilling
works on top of SCL protection works. Pre-bored
H piling works for the proposed CWB and altogether 10 nos. and 9 nos. of
pre-bored H piles. Pre-drilling
works for CWB (Stage 2). Ground
treatment works for proposed CWB diaphragm wall. Plant
Mobilization for diaphragm wall construction works at Stage 2. E&M Full
commissioning test for Cooling Water Pumping Station P1
Site test for all E&M equipment and
facilities in Cooling Water Pumping Station P5 |
Marine
Works (at Wan Chai) Rockfilling
at the northern part of HKCEC3E (East of HKCEC) between CH290 and CH385. Rockfilling
at the southern part of HKCEC3E (East of HKCEC) between CH290 and CH385 for
subsequent open channel construction. Installation
of precast block seawall (Type 1, 2 & 3). Construction
of mass concrete coping for new seawall. Cross-Harbour
Watermains Installation (CHA & CHB) and Marine Works (at TST) Rockfilling
and rock protection to cross-harbour watermains. Reinstatement
works including seawall coping, gully, drawpit and tree transplantation for
the TST landfall. CCTV
inspection for cross-harbour water main (including CHA, CHB, CHE & CHF). Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land) Mainlaying
works at Zone B6-1, B6-3, B6-5, A1-2A & A1-3A, A3-3C and C1-2 . Mainlaying
works and substantially reinstatements in Zone A1-2, A2-3D (Stage 2), C1-4
and A3-4A. Grouting,
pipe connection and reinstatement works in combined Zone A1-2A & A1-3A. Grouting,
pipe connection and reinstatement works in Zone A1-3B. Mainlaying
works and substantially reinstatements in Zone A3-5A, A3-3B and footpath of Preparation
works at Zone A3-3C for subsequent connection works. The
preparation works (including exposure of installed gate valve and repair of
butterfly valve) at The
preparation works (including exposure of installed gate valve and repair of
gate valve) at Mainlaying
works at Zone C1-2. Mainlaying
works and coring works at external wall of seawater pumping stations for
proposed sewerage system in Zone B6-1. Mainlaying
works and substantially reinstatements in Zone B6-3 (previously named B1-5A)
and B6-5 (previously named B2-1). Final
cleaning, CCTV inspection and pressure test for the 9 nos. cooling
watermains. CCTV
inspection for cross-harbour watermains (land pipe at Wan Chai). Pressure
test for cross harbour watermains (whole length of land pipes in Wan Chai). Trench
excavation for HEC and PCCW cabling works connected to the proposed
transformer rectifier at new reclaimed area. Tunnel
Works Backfilling
works on top of SCL protection works. Pre-bored
H piling works for the proposed CWB stage 1b Pre-drilling
works for CWB (Stage 2). Diaphragm
wall construction works at Stage 2. Removal of
remaining guide wall along E & M Full
commissioning test for Cooling Water Pumping Station P1. Site test
for all E&M equipment and facilities in Cooling Water Pumping Station P5. Initial
commissioning test for Cooling Water Pumping Station P5. |
2.5.2.
During
this reporting period, the principal work activities for Contract no.
HK/2009/02 are summarized in Table 2.5.
Table
2.5 Principal Work Activities for
Contract no. HK/2009/02
December
2012 |
January 2013 |
February
2013 |
Concreting
the slab with hanger wall for planting area (+13.55mPD) between G.L.3-6/B-C
& E-F on Observation Deck Level (+14.65mPD) Concreting
the base slab and wall of sprinkler water tank machine room and the slab of
Machine Room Installation
of concrete block wall for store room 1 and room 2 on Level 1 Erecting
the wall stem formwork for caisson seawall precast unit 2X on flat-top barge Modification
work of PTI at Modification
work of bus station at Breaking
up the existing covered walkway footing at Rectification
works at bending block of cooling mains E&M
works and ABWFs installation at WSD Salt Water Pumping Station Drilling
hole and installation of pipe bracket for aeration and chlorination pipe
inside salt water intake Concreting
of the structure at salt water intake Steel
fixing of the shaft of Bay 2a in salt water intake seaside cofferdam Breaking
the existing concrete road slab for DN800 salt water mains at Ex-pet garden
near gate 1 Installation
the shoring to trial pit of the permanent connection point to existing DN 600
water main at Installation
of precast concrete short pipe extended from the existing 1800 drainage at
Box Culvert N landside |
Modification
work of PTI at Concreting
the retaining wall base slab of Bay1, Bay 2 and Bay 5 at Rectification
works at bending block of cooling mains. E&M
works and ABWFs installation at WSD Salt Water Pumping Station. Concreting
infill mass concrete at both sides and concreting 1m width x 300mm high mass
for cover M.J. at Bay 9 to Bay 11 in salt water intake landside cofferdam. Backfilling
grade 200mm rock material in the trench at Bay 6 to Bay 8 in salt water
intake landside cofferdam. Drilling
hole and installation of pipe bracket for aeration and chlorination pipe
inside salt water intake The shafts
of Intake chamber No.1 and No.2 for Bay 2A in salt water intake seaside
cofferdam were casted the 2nd layer of the horizontal struts. Placing
concrete for bend blocks btw CHS8A 150-165 at Ex-pet garden near new Gate
No.2. Installation
the shoring to trial pit of the permanent connection point to existing DN 600
water main at Saw
cutting of southern diaphragm wall for the connection between existing
drainage and Bay 1 of box culvert N1. Laying
1800mm dia. concrete pipe for the connection between existing drainage and
Bay 1 of box culvert N1. Erecting
formwork for concrete surround for concrete pipe. Concreting
of columns (total 6nos.) from M/F (+11.15mPD) to Observation Deck Level
(+14.65mPD) and Slab with beam between G.L.1-3/B-F on Level 2 (+7.65mPD). Concreting
of columns (total 9nos.) from Level 2 (+7.65mPD) to Observation Deck Level
(+14.65mPD). Concreting
of portion 2 for column C2C from +11.65mPD to +13.90mPD up to Observation
Deck Level (+14.65mPD). Concreting
of portion 1 for column C2E from +7.65mPD to +11.65mPD up to Observation Deck
Level (+14.65mPD). Steel
fixing and Formwork erection to Observation Deck Level at from GL 3-8 &
9-15. Installation
of concrete block wall for store room 1 and room 2 on Level 1. Placing
concrete of the final portion for precast scission seawall 2X. |
Modification
work of PTI at Modification
of existing covered walkway along Pressure
tests and the necessary rectification works for the installed cooling watermains. Backfilling
for trench at the junction between E&M
works and their T&C in Cooling Water Pumping Stations P7, P8 and P9. Wet Tests
at WSD Salt Water Pumping Station. Backfilling
grade Drilling
hole and installation of pipe bracket for aeration and chlorination pipe
inside salt water intake Diver work
for excavation down to formation level at Bay 1B in salt water intake seaside
cofferdam. Mainlaying
works for DN800 salt watermains (CHS Works for
the Outfall B had been and the dye test. Switching
over works for sewage to WCE PTW. RC
structures for the proposed Ferry Pier. Construction
of eastern concrete staircase to Observation Deck Level. Concreting
of base slab with stem wall for PT2 & PT3 at Level 1 (under +4.15mPD). Installation
of concrete block wall for store room 1 and store room 2 on Level 1. Application
of protective coating to proposed precast caisson seawall 2X Eastern
Bulkhead Wall, Panel BHP3, BHP7 and BHP9 were cast (3 out of 13 panels) and
excavation for Panel BHP5. |
2.5.3.
Major construction activities for Contract no.
HY/2009/15 was commenced on 10 November 2010. During this reporting period, the
principal work activities for Contract no. HY/2009/15 are summarized as below:
Table
2.6 Principal Work Activities for
Contract no. HY/2009/15
December
2012 |
January 2013 |
February
2013 |
TZ1 and
TS2 reclamation works Formation
of temporary seawall at TS2 |
TZ1 and
TS2 reclamation works Formation
of temporary seawall at TS2 |
Removal of
eastern breakwater of CBTS |
2.5.4.
Contract
no. HK/2010/06 was commenced on 22 March 2011. During this reporting period,
the principal work activities for Contract no. HK/2010/06 are summarized as
below:
Table
2.7 Principal Work Activities for
Contract no. HK/2010/06
December
2012 |
January 2013 |
February
2013 |
Sheet
piling Platform
Disassembly Bored pile
casing cutting Grouting |
Disassembly
of staging platform Pile case cutting Sheet pile
installation Dredging Construction
of pre-cast unit in mainland |
Sheet
Piling Works Utility
Diversion Works Precast
Unit Box Construction (mainland |
Table 2.8 Principal Work Activities for Contract no. HY/2009/19
December
2012 |
January 2013 |
February
2013 |
Marine
bored piling Construction
works for Box Culvert T Construction
of 1500f
drainage pipe |
Road works
at Bored
piling (Land) Pre-drilling
works for bored pile and Diaphragm wall D-wall Construction
(North & South Section) Guide wall
construction for D-wall / Barrette at North side Construction
works for Box Culvert T1 Marine
Piling Construct
ion of socket-H pile Construction
works for Culvert U1 Construction
of Pile cap & column (Land) Dismantling
of marine platform Demolition
of parapet at IEC Link Construction
of Pile caps & columns (Marine) Cut &
Cover Tunnel sheet piling works and installation of King Post Construction
of dewatering well for Cut & Cover Tunnel |
Road works
at Bored
piling (Land) D-wall Construction
(North & South Section) Guide wall
construction for D-wall / Barrette at North side Construction
works for Box Culvert T1 Marine
Piling Construct
ion of socket-H pile Construction
works for Culvert U1 Construction
of Pile caps & columns (Land) Dismantling
of marine platform Demolition
of parapet at IEC Link Construction
of Pile caps & columns (Marine) Construction
of dewatering well for Cut & Cover Tunnel D8-D9
Gantry Fabrication for precast segment will continue ELS for
Cut & Cover Tunnel will continue |
2.5.6.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix 2.1.
Noise Monitoring Stations
3.1.1. The noise monitoring stations for the Project
are listed and shown in Table 3.1 and Figure 3.1. Appendix 3.1 shows the established Action/Limit
Levels for the monitoring works.
Table
3.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Real
time Noise Monitoring Stations
3.1.1.
The real-noise monitoring stations for the Project are
listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1 shows the established Action/Limit Levels for
the monitoring works.
Table
3.2 Real Time Noise
Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
North Point |
RTN2a |
Electric Centre |
Noise Monitoring
Parameters, Frequency and Duration
3.1.2. The construction noise level
shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period
between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq
(5 minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.3. Noise monitoring shall be
carried out at all the designated monitoring stations. The monitoring frequency
shall depend on the scale of the construction activities. The following is an
initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
·
one
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.4. If construction works are extended to include works
during the hours of 1900 – 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
3.1.5. Real time noise shall be carried out at the
designated monitoring stations. The following is an initial guide on the
regular monitoring frequency for each station on a 24 hours daily basis when
noise generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
Monitoring Equipment
3.1.6. As referred
to in the Technical Memorandum ™ issued under the NCO, sound level meters in
compliance with the International Electrotechnical Commission Publications 651:
1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying
out the noise monitoring. Immediately prior to and following each noise
measurement the accuracy of the sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.7. Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
Air Quality Monitoring
Stations
3.2.1.
The
air monitoring stations for the Project are listed and shown in Table
3.3 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the
monitoring works.
Table
3.3 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
* Remarks: As per the ENPC
meeting in January 2011, the monitoring stations CMA3a - Future CWB site office
at Wanchai Waterfront Promenade and CMA6a - Future AECOM site office at Work
Area were renamed as remark.
Air Monitoring Parameters,
Frequency and Duration
3.2.2.
One-hour
and 24-hour TSP levels should be measured to indicate the impacts of
construction dust on air quality. The 24-hour TSP levels shall be measured by
following the standard high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
3.2.3.
All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and any other local atmospheric factors affecting or
affected by site conditions, etc., shall be recorded down in detail.
3.2.4.
For
regular impact monitoring, the sampling frequency of at least once in every
six-days, shall be strictly observed at all the monitoring stations for 24-hour
TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least
three times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5 High
volume samplers (HVSs) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6
- 1.7 m3 per minute adjustable flow range;
·
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
capable
of providing a minimum exposed area of 406 cm2;
·
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
equipped
with a shelter to protect the filter and sampler;
·
incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
equipped
with a flow recorder for continuous monitoring;
·
provided
with a peaked roof inlet;
·
incorporated
with a manometer;
·
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
easily
changeable filter; and
·
capable
of operating continuously for a 24-hour period.
3.2.6 Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognized primary standard and be calibrated
annually. The concern parties such as IEC shall properly document the
calibration data for future reference. All the data should be converted into
standard temperature and pressure condition.
Laboratory Measurement /
Analysis
3.2.7 A clean
laboratory with constant temperature and humidity control, and equipped with
necessary measuring and conditioning instruments to handle the dust samples
collected, shall be available for sample analysis, and equipment calibration
and maintenance. The laboratory should be HOKLAS accredited.
3.2.8 An
alternative non-HOKLAS
accredited laboratory was set-up for carrying out the laboratory
analysis, the laboratory equipment was approved by the ER on 8
February 2011 and
the measurement procedures were witnessed by the IEC. Any measurement performed by
the laboratory was be demonstrated to the satisfaction of the ER and IEC. IEC shall
regularly audit to the measurement performed by the laboratory to ensure the
accuracy of measurement results.
3.2.9 Filter
paper of size 8" x 10" shall be labelled before sampling. It shall be
a clean filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
3.2.10 After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
3.2.11 All the
collected samples shall be kept in a good condition for 6 months before
disposal.
impact monitoring for
odour patrol
3.2.12 Odour patrols along the
shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai Public Cargo Working
Area when there is temporary reclamation in Causeway Bay Typhoon Shelter and/or in the ex-Wan Chai Public Cargo
Working Area, or when there is dredging of the odorous sediment and slime at
the south-western corner of the Causeway Bay Typhoon Shelter. Odour patrols
will be carried out at bi-weekly intervals during July, August and September by
a qualified person of the ET who shall:
·
be
at least 16 years of age;
·
be
free from any respiratory illnesses; and
·
not
be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30
min
·
before
and during odour patrol
3.2.13 Odour patrol shall be conducted by independent
trained personnel / competent persons patrolling and sniffing around the shore
as shown in Figure 3.1 to detect any odour at
the concerned hours (afternoon is preferred for higher daily temperature).
3.2.14 The qualified person will use the nose (olfactory
sensor) to sniff odours at different locations. The main odour emission sources
and the areas to be affected by the odour nuisance will be identified.
3.2.15 The perceived odour intensity is to be divided into
5 levels which are ranked in the descending order as follows:
·
0 -
Not detected. No odour perceived or an odour so weak that it cannot be easily
characterized or described;
·
1 -
Slight Identifiable odour, and slight chance to have odour nuisance;
·
2 -
Moderate Identifiable odour, and moderate chance to have odour nuisance;
·
3 -
Strong Identifiable, likely to have odour nuisance;
·
4 -
Extreme Severe odour, and unacceptable odour level.
3.2.16 The findings including odour intensity, odour
nature and possible odour sources, and also the local wind speed and direction
at each location will be recorded. In addition, some relevant meteorological
and tidal data such as daily average temperature, and daily average humidity,
on that surveyed day will be obtained from the Hong Kong Observatory Station
for reference. The Action and Limit levels for odour patrol are shown in Appendix 3.1.
3.3.1. The EIA Report has identified that the key water
quality impact would be associated with the dredging works during the
construction phase. Marine water quality
monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is
therefore recommended to be carried out at selected WSD flushing water
intakes. The impact monitoring should be
carried out during the proposed dredging works to ensure the compliance with
the water quality standards.
3.3.2. The updated
EM&A Manual for EP-356/2009 (Version in March 2011) is approval by EPD on
29 April 2011. As such, the Action Level and Limit Level for the wet season
(April – September) will be effected and applied to the water quality
monitoring data from 30 April 2011.
Water Quality Monitoring Stations
3.3.3. It is proposed to monitor the water quality at 9
WSD salt water intakes and 14 cooling water intakes along the seafront of the
Table
3.4
Marine Water Quality Stations for Water
Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
|
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW1 |
Wan Chai (Reprovision) |
836188.8 |
815911.1 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Wan |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
C6 |
World Trade Centre |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150.0 |
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
RC1 |
Proposed HKAPA Extension |
835487.7 |
815987.7 |
RC5 |
Sun Hung Kai Centre (Reprovision) |
836291.4 |
816029.7 |
RC7 |
|
837245.2 |
816156.6 |
Remarks: - The cessation of
seawater intake operation for C6 was confirmed on 17 May 2011, the water
monitoring at C6 was then terminated since 17 May 2011.
- WSD9 and WSD17 were implemented with respect
to HK/2009/02 from 8 Feb 2012.
- 4-week water quality monitoring at WSD9,
WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.
- C8 and C9 were implemented with respect to
HY/2009/19 from 28 Jan 2012.
- WSD7 and WSD20 water quality monitoring were
temporarily suspended from 27 Apr 2012.
Water Quality Parameters
and frequency
3.3.4. Monitoring of dissolved oxygen (DO), turbidity and
suspended solids (SS) shall be carried out at WSD flushing water intakes and
cooling water intakes. DO and Turbidity are measured in-situ while SS is
determined in laboratory.
3.3.5. In association with the water quality parameters,
other relevant data shall also be measured, such as monitoring
location/position, time, sampling depth, water temperature, pH, salinity,
dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal
stage, and any special phenomena and work underway at the construction site
etc.
3.3.6. The interval between two sets of monitoring should
not be less than 36 hours except where there are exceedances of Action and/or
Limit Levels, in which case the monitoring frequency will be increased. Table 3.5 shows the proposed
monitoring frequency and water quality parameters. Duplicate in-situ measurements and water
sampling should be carried out in each sampling event. For selection of tides for in-situ
measurement and water sampling, tidal range of individual flood and ebb tides
should be not less than 0.5m.
Table
3.5 Marine Water Quality Monitoring Frequency
and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week
baseline monitoring period |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine construction works |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
After completion of marine construction works |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1. For
selection of tides for in-situ measurement and water sampling, tidal range of
individual flood and ebb tides should be not less than 0.5m.
2.
Turbidity should be
measured in situ whereas SS should be determined by laboratory.
Dissolved Oxygen and
Temperature Measuring Equipment
3.3.7. The instrument should be a portable, weatherproof
dissolved oxygen measuring instrument complete with cable, sensor,
comprehensive operation manuals, and use a DC power source. It should be
capable of measuring:
·
a
dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation
·
a
temperature of 0-45 degree Celsius
3.3.8. It should have a membrane electrode with automatic
temperature compensation complete with a cable. Sufficient stocks of spare
electrodes and cables should be available for replacement where necessary.
(e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel
and cable or an approved similar instrument).
3.3.9. Should salinity compensation not be build-in in the
DO equipment, in-situ salinity shall be measured to calibrate the DO equipment
prior to each DO measurement.
Turbidity Measurement
Instrument
3.3.10 The
instrument should be a portable, weatherproof turbidity-measuring instrument
complete with comprehensive operation manual. The equipment should use a DC
power source. It should have a photoelectric sensor capable of measuring
turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach
model 2100P or an approved similar instrument).
Sampler
3.3.11 Water sampler comprises a transparent PVC
cylinder, with a capacity of not less than 2 litres, and can be effectively
sealed with latex cups at both ends. The sampler should have a positive
latching system to keep it open and prevent premature closure until released by
a messenger when the sampler is at the selected water depth (e.g. Kahlsico
Water Sampler or an approved similar instrument).
Sample Container and
Storage
3.3.12 Water
samples for suspended solids measurement should be collected in high-density
polythene bottles, packed in ice (cooled to 4°C without being frozen), and
delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection
for analysis.
Water Depth Detector
3.3.13 A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be
handheld or affixed to the bottom of the workboat, if the same vessel is to be
used throughout the monitoring programme.
Salinity
3.3.14 A portable
salinometer capable of measuring salinity in the range of 0-40 ppt shall be
provided for measuring salinity of the water at each of monitoring location.
Monitoring Position
Equipment
3.3.15 A
hand-held or boat-fixed type digital Global Positioning System (GPS) with
waypoint bearing indication or other equivalent instrument of similar accuracy
shall be provided and used during monitoring to ensure the monitoring vessel is
at the correct location before taking measurements.
Calibration of In-situ
Instruments
3.3.16 All
in-situ monitoring instrument shall be checked, calibrated and certified by a
laboratory accredited under HOKLAS or equivalent before use, and subsequently
re-calibrated at 3 monthly intervals throughout all stages of the water quality
monitoring. Responses of sensors and electrodes should be checked with
certified standard solutions before each use. Wet bulb calibration for a DO
meter shall be carried out before measurement at each monitoring location.
3.3.17 For the on
site calibration of field equipment by the ET, the BS 127:1993, "Guide to
Field and on-site test methods for the analysis of waters" should be
observed.
3.3.18 Sufficient
stocks of spare parts should be maintained for replacements when necessary. Backup
monitoring equipment shall also be made available so that monitoring can
proceed uninterrupted even when some equipment is under maintenance,
calibration, etc.
Laboratory Measurement /
Analysis
3.3.19 Analysis
of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS
Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the
monitoring stations for carrying out the laboratory SS determination. The SS
determination work shall start within 24 hours after collection of the water
samples. The SS determination shall follow APHA 19ed or equivalent methods
subject to the approval of IEC and EPD.
Enhanced Water Quality
Monitoring in the ex-Wan Chai Public Cargo
Working Area and the
3.3.10. The enhanced water quality monitoring and audit
programme is to avoid aggravation of odour nuisance from seawater arising from
temporary reclamation in the ex-Wan Chai Public Cargo Working Area and the
Causeway Bay Typhoon Shelter.
3.3.11. Dissolved oxygen monitoring at the intakes C6 and
C7 in Causeway Bay Typhoon Shelter when there is temporary reclamation in
Causeway Bay Typhoon Shelter and at the south-western and south-eastern corners
of the ex-Wan Chai Public Cargo Working Area. The proposed water quality
monitoring stations of the Project are shown in Table 3.6 and Figure 3.1.
Table 3.6 Marine
Water Quality Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior Hotel |
C7 |
|
Ex-WPCWA-SW |
South-western of the ex-Wan Chai
Public Cargo Working Area |
Ex-WPCWA-SE |
South-eastern of the ex-Wan Chai
Public Cargo Working Area |
3.3.12. The monitoring of dissolved oxygen are to be
carried out 3 days per week, at mid-flood and mid-ebb tides for 3 water depths
(1m below water surface, mid-depth and 1m above sea bed, except where the water
depth less than 6m, the mid-depth may be omitted. If the water depth be less
than 3m, only the mid-depth will be monitored).
Daily SS Monitoring and 24
hours Turbidity Monitoring System
3.3.13. During dredging of the sediment at the
south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of suspended solids and 24 hour monitoring
of turbidity at the cooling water intakes (C6 and C7) shall be conducted.
3.3.14. The 24 hours monitoring of turbidty at the cooling water
intakes (C6 and C7) shall be established by setting up a
continuous water quality monitoring station in front of the intakes during the
dredging activities. The monitoring
system include the turbidity sensor and data logger which is capable of data capturing at every 5 minutes. The data shall be downloaded daily and compared with the Action and Limit
level determined during the baseline water qualtiy monitoring at the cooling
water intake locations.
Additional Dissovled
oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW
3.3.15
In response to the Condition 2.18 of the Environmental Permit no.
EP-356/2009 requiring that a silt curtain / impermeable barrier system be
installed to channel water discharge flow from Culvert L to locations outside
the embayment area, a proposed replacement of the requirement with additional
dissolved oxygen monitoring has been conducted at three monitoring stations,
namely A, B and C between the eastern seawall of Central Reclamation Phase III
and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level
between the eastern seawall of Central Reclamation Phase II and the HKCEC
extension could be continuously monitored.
3.3.16 The proposed DO monitoring
stations of the Project are shown in Table 3.7
Table 3.7 Marine Water Quality Stations for Additional
DO Monitoring
Station |
Easting |
Northing |
A |
835468 |
815857 |
B |
835572 |
815961 |
C |
835659 |
816271 |
3.3.17
The monitoring of dissolved oxygen are to be carried out once per week,
at mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be equal to or less than 3m, only
the mid-depth will be monitored).
4.0.1. The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown
in
Figure
2.1 and Figure 3.1. The monitoring
results are presented in according to the Individual Contract(s).
4.0.2 The
major work activities for Contract no. HY/2009/11 was confirmed substantial
complete by RSS on 4 January 2012. The FEP surrender application
was submitted to EPD by contractor on 16 Jan 2012 that they would
surrender the permit on 1 Jan 2012. Moreover, the construction site was
handed over to contractor HY/2009/19 on 4 January 2012. However, the surrender
of the FEP for HY/2009/11 withdrew by contractor on 14 February 2012 due to
some outstanding works was confirmed by RSS on 10 Feb 2012.
Therefore, the noise, air and water quality monitoring were keeping in
view for the commencement of the works under this contract. No
construction activity was conducted by HY/2009/11 up to 4 January 2012.
4.0.3 According to EP-364/2009/A
Part B, “Scale and Scope of Designated Project”, Remarks (c),”The permanent and
temporary reclamation and associated dredging works related to the CWB
construction are separately covered by environmental permit No. EP-356/2009
issued to Civil Engineering and Development Department”, and marine piling
works to be conducted by the Contractor of Contract no. HY/2009/19 from 28
January 2012 was considered to be governed under EP-356/2009. As the
construction site area of Contract no. HY/2009/11 had already been handed over
to Contract no. HY/2009/19, the designated noise, water and air quality
monitoring stations for Contract no. HY/2009/11 would be shared with Contract
no. HY/2009/19 from 28 January 2012.
Contract no. HK/2009/01 - Wan Chai Development
Phase II – Central –Wanchai Bypass at HKCEC and Contract no. HK/2009/02 - Wan
Chai Development Phase II – Central – Wan Chai Bypass at WanChai East and Contract
no. HK/2010/06 Wan Chai Development Phase II – Central-Wan Chai Bypass over MTR
Tsuen Wan Line
4.1.1.
The
proposed divisions of noise monitoring stations are summarized in Table
4.1 below.
Table 4.1 Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02 and HK/2010/06
Station |
Description |
M1a |
Harbour Road Sports Centre |
4.1.2.
No
action level and two limit level exceedance was recorded on 24 and
29 Jan 2013 in the reporting quarter. Non-CWB project drilling works nearby was observed
during noise monitoring and considered as the major noise contribution. As such, the exceedance was not related to
the Project. Details of noise monitoring results and graphical presentation can
be referred in Appendix 4.1.
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
4.1.3. The noise monitoring for HY/2009/15 was
commenced on 10 November 2010. The
proposed division of noise monitoring stations are summarized in Table
4.2 below.
Table
4.2
Noise Monitoring Station for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.4.
There was no exceedance recorded
in this reporting period.
The noise complaint was recorded on 5 April 2012. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1
Contract no. HY/2009/19 – Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
4.1.5.
Noise
quality monitoring at M4b and M5b have been implemented with respect to
HY/2009/19 since the marine bore piling work started on 28 Jan 2012.
4.1.6.
The
proposed division of noise monitoring stations for Contract no. HY/2009/19 are
summarized in Table 4.3 below:
Table 4.3
Noise Monitoring
Stations for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
4.1.7. Thirteen limit level exceedance was recorded at M6
on 29 November 2012, 11, 17 and 27 December 2012, 3, 8, 15, 24 and 29 January 2013, 7, 15, 19
and 26 February 2013 during this reporting quarter. Major traffic jam and no
major work activities were observed during monitoring, the exceedances were
considered as non-project related. Noise monitoring results measured in this
reporting period are reviewed and summarized.
Details of graphical presentation can be referred in Appendix 4.1.
4.2.1 As the land-based piling
and filling works- DP3 at Tin Hau had been completed on 3 September 2012 and
confirmed by RSS, the real-time noise monitoring results at FEHD Hong Kong
Transport Section Whitfield Depot was excluded under EP-356/2009 since 28
November 2012.
4.2.2 The real-time noise
monitoring results at RTN1 (FEHD Hong Kong Transport Section Whitfield
Depot) was excluded under EP-356/2009 since 28 October 2012, as the land-based
piling and filling works- DP3 at Tin Hau had been completed on 3 September 2012
and confirmed by RSS
4.2.3 Oil Street Community Liaison Centre was confirmed
to be demolished in mid-October by CWB RSS.
This presented a need for relocation of RTN2 – Oil Street Community
Liaison Centre. After liaison with Hong
Kong Electric, permission was granted on 21 Sep 2012 for real time noise
monitoring set up at City Garden Electric Centre (RTN2a – Electric Centre),
which is a representative of the noise sensitive receiver City Garden. The real-time noise monitoring at RTN2-Oil
Street Community Liaison Centre has been relocated to City Garden Electric
Centre (RTN2a- Electric Centre) on 5 Oct 2012. The baseline noise level of
RTN2a will adopt the results derived from the baseline noise monitoring
conducted in Electric Centre from 4 December 2009 to 17 December 2009.
Contract no. HY/2009/19 – Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
4.2.4
The
proposed divisions of real time noise monitoring stations are summarized in Table
4.4 below. Real time noise monitoring for the marine bored piling works
under contract no. HY/2009/19 was commenced on 28 January 2012.
4.2.5
Real-time
noise monitoring at FEHD Hong Kong Transport Section Whitefield Depot commenced
external wall renovation since 1 June 2012
4.2.6 The
major work activities for Contract no. HY/2009/11 was confirmed substantial complete
by RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19 on 31 December 2011 in
this reporting period and the FEP-01/356/2009 was
surrendered on 22 October
2012.
The monitoring was temporary suspended since 5 January 2012.
4.2.7 Limit level exceedance was recorded at
RTN2a-Electric Centre on 7 Dec 2012 in the reporting quarter. After checking
with contractor, no major noisy construction works were conducted during the
time period and the non CWB project construction activities near Electric
Centre was considered to be the major source of noise impact. As such, the
exceedance was concluded as non-project related.
4.2.8 Limit level exceedances were
recorded at RTN2a-Electric Centre during daytime on 31 Jan 2013 and during
restricted hours on 5, 11 and 12 Feb 2013. After checking with contractor, on
31 Jan 2013, no noisy construction activities were undertaken during the
recorded period. The exceedance was non-continuous and considered to be
contributed by the IEC traffic. On 11 and 12 Feb 2013, no construction
activities were conducted and the exceedances were considered to be contributed
by the Chinese New Year pyrotechnic display and IEC traffic respectively. As
such, the exceedances were concluded as non-project related. Appendix
4.2
Table 4.4 Real Time Noise Monitoring Station for Contract no. HY/2009/11 and HY/2009/19
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section
Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
North Point |
RTN2a |
Electric Centre |
l
Real time noise
monitoring results and graphical presentation during night time period are for
information only.
l
RTN2 had been relocated to RTN2a since 5 Oct 2012
l
RTN1 monitoring had been finished on 28 Nov 2012
4.3.1.
Due to extension of site boundary by contractor of
HY/2009/19, location of air monitoring station CMA1b – Oil Street Community
Liaison Centre has been finely adjusted on 21 April 2012.
4.3.2.
Due to lack of electricity supply, the 24-hr TSP
monitoring at the following stations were rescheduled
CMA2a: from 13 December 2012 to 14 December
2012
CMA3a: from 22 December 2012 to 24 December
2012
from 26 Jan 2013 to 28 Jan 2013
CMA6a: from 1 December 2012 to 3 December
2012
CMA5a:
from 26 Feb 2013 to 27 Feb 2013
Contract no. HY/2009/11 – Central –
Wanchai Bypass, North Point Reclamation
4.3.3.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 and the FEP-01/356/2009
was surrendered on 22 October 2012. The monitoring for the contract was
temporary suspended on 6 January 2012.
Contract no. HK/2009/01 - Wan Chai Development
Phase II – Central –Wanchai Bypass at HKCEC
4.3.4.
Air
monitoring was commenced on 1 April 2011 in response to the commencement of the
land-filling work for Contract no. HK/2009/01. The proposed division of air
monitoring stations are summarized in Table 4.6
below. No exceedance was recorded in the reporting period.
Table 4.6 Air Monitoring
Stations for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
CMA6a |
WDII PRE Site Office * |
Contract no. HK/2009/02 - Wan Chai Development
Phase II – Central – Wan Chai Bypass at WanChai East
4.3.5.
Air
monitoring was commenced in mid-January 2011 for the land-filling work for
Contract no. HK/2009/02. The proposed division of air monitoring stations is
summarized in Table 4.7 below. No exceedance was recorded in the
reporting period.
Table 4.7 Air Monitoring Station
for Contract
no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
4.3.6. Air monitoring was commenced on 15 March 2011 for
the land filling work for Contract no. HY/2009/15. The proposed division of air monitoring
stations are summarized in Table 4.8 below. No
exceedance was recorded in the reporting period.
Table
4.8
Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB site office at Wanchai
Waterfront Promenade |
Contract no. HY/2009/19 –Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
4.3.7.
Air monitoring at CMA1b and CMA2a have been
implemented with respect to HY/2009/19 since the marine bore piling works
started on 28 Jan 2012. No exceedance was recorded in the reporting
period.
4.3.8.
The proposed division of air monitoring stations is
summarized in Table 4.9 below.
Table
4.9 Air
Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
|
Contract no. HY/2009/11 – Central – Wanchai Bypass,
North Point Reclamation
4.4.1. The major
work activities for Contract no. HY/2009/11 was confirmed substantial complete
by RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19 on 31 December 2011 and the FEP-01/356/2009 was valid in this
reporting period.
4.4.2.
Water quality monitoring for Contract no. HY/2009/11 was
commenced on 19 March 2010. The proposed division of water monitoring stations
for Contract no. HY/2009/11 is summarized in Table 4.10 below:
Table
4.10 Water Monitoring Stations for Contract no. HY/2009/11
Station
Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo
Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
|
839790.3 |
817032.2 |
Cooling Water Intake |
|||
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
Remarks:
WSD9, WSD10, WSD15, WSD17. C8 and C9 water monitoring finished on 6 Feb 2012.
Contract no. HK/2009/01 - Wan Chai Development
Phase II – Central –Wanchai Bypass at HKCEC
4.4.3.
Water quality monitoring for Contract no. HK/2009/01 was
commenced on 23 July 2010. The proposed division of water monitoring stations
is summarized in Table 4.11 below.
4.4.4.
Due to the blockage of road access to C1 on 15 Dec 2012 during mid-flood,
the water quality monitoring was cancelled at C1 on 15 December 2012 during
mid-flood.
4.4.5.
Due to the blockage of road access to C2 on 7 Jan 2013 during mid-flood,
the water quality monitoring at C2 was cancelled on 7 Jan 2013 during
mid-flood.
Table 4.11 Water Monitoring Stations for Contract no. HK/2009/01
Station
Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
Cooling Water Intake |
|||
C1 |
HKCEC
Extension |
835885.6 |
816223.0 |
C2 |
Telecom
House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase
I |
835836.2 |
815910.0 |
C4e |
Wan |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
Remarks:
- The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations have not been carried out by others.
-
WSD7 and WSD20 water quality monitoring were temporarily suspended since
27 Apr 2012.
Contract no. HK/2009/02 - Wan Chai Development Wan
Chai Development Phase II – Central – Wan Chai Bypass at WanChai East
4.4.6.
Water
quality monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010.
The proposed division of water monitoring stations is summarized in Table
4.12 below.
4.4.7.
Due to the blockage of road access to C5e and C5w on 7 Jan 2013 during
mid-ebb tide and 9, 11, 14 Jan the sample was taken under contingency C5 on 7 Jan
2013 during mid-ebb and 9, 11, 14 Jan during mid-flood and mid-ebb.
4.4.8.
Due to the lack of lighting on the road access to
C5e and C5w on 4 Feb 2013 during mid-ebb tide the sample was taken under
contingency C5 on 4 Feb 2013 during mid-ebb
Table 4.12 Water Monitoring Stations for Contract no. HK/2009/02
Station
Ref. |
Location |
Easting |
Northing |
|||
WSD Salt Water Intake |
||||||
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
|||
WSD9 |
Sheung Wan |
833415.0 |
816771.0 |
|||
WSD17 |
|
830750.6 |
816030.3 |
|||
Cooling Water Intake |
||||||
C5e |
Sun Hung
Kai Centre (Eastern) |
836250.1 |
815932.2 |
|||
C5w |
Sun Hung
Kai Centre (Western) |
836248.1 |
815933.2 |
|||
Remarks:
-
The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations has not been carried out by others.
-
Water
quality monitoring at WSD9 and WSD 17 was implemented with respect to
HK/2009/02 from 8 Feb 2012.
Contract no. HK/2010/06 - Wan Chai
Development Phase II – Central –Wanchai Bypass over MTR Tsuen Wan Line
4.4.9.
Water
monitoring for Contract no. HK/2010/06 was commenced on 8 March 2011. The
proposed division of water monitoring stations are summarized in Table 4.13
below.
4.4.10.
Due to the blockage of road access to C2 on 7 Jan 2013 during mid-flood,
the water quality monitoring at C2 was cancelled on 7 Jan 2013 during
mid-flood.
Table
4.13
Water Monitoring Stations for Contract
no. HK/2010/06
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C2 |
Telecom
House |
835647.9 |
815864.4 |
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (
4.4.11.
Due to the commencement of the
maintenance dredging on 10 November 2010, water quality monitoring for Contract
no. HY/2009/15 was commenced on 9 November 2010. The proposed division of water
monitoring stations is
summarized in Table 4.14 below.
Table
4.14 Water Monitoring Stations for Contract no.
HY/2009/15
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C6 |
Excelsior Hotel |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150 |
Remarks: - The cessation of seawater intake operation for C6
was confirmed on 17 May 2011, the water monitoring at C6 was then terminated
since 17 May 2011.
Contract no. HY/2009/19 – Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
4.4.12. Due to the
commencement of the marine bored piling on 28 Jan 2012, water quality
monitoring for Contract no. HY/2009/19 was commenced on 28 Jan 2012. The
proposed division of water monitoring stations are summarized in Table
4.15 below.
4.4.13.
As confirmed by HY/2009/19 contractor, there was no marine work to be
conducted on 26 December 2012, water quality monitoring at C8 and C9 were
temporary suspended on 26 December 2012 during mid-ebb and mid-flood.
Table 4.15
Water
Monitoring Stations for Contract no. HY/2009/19
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident
Garden |
838355.0 |
817116.6 |
Remarks: C8 and C9 water monitoring
commenced on 28 Jan 2012.
4.4.14.
Water quality monitoring was cancelled on 12 February 2013 due to
closing of construction site within the Chinese New year
4.4.15.
Based on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week
water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no
water deterioration with respect to NPR was commenced since 7 Jan 2012 and it
was completed on 6 February 2012.
4.4.16.
Water quality monitoring at WSD10 and WSD15 was temporary suspended while
water quality monitoring at WSD9 and WSD17 was implemented with respect to
HK/2009/02 from 8 Feb 12 onwards;
4.4.17.
Water quality monitoring at C8 and C9 have been implemented with respect
to HY/2009/19 since the marine bore piling work started on 28 Jan 12.
4.4.18.
Based on the safety concern when external façade refurbishment was
conducted by contractor employed by Provident Center (C9) between 9 January
2012 to 30 July 2012 which caused to the inaccessibility of sampling either
land and marine since 3 Feb 2012, there is a fine adjustment of the sampling
location of water quality monitoring at C9 since 10 March 2012 to the closest
accessible point prior to the completion of the external façade refurbishment
work.
4.4.19.
With respect to the trial dredging at WCR2 was scheduled on 20, 22, 24,
25 March and 1, 3 , 11, 13, 15, 17, 19, 20 Apr and 3 May 2012, on-going water
quality monitoring results at WSD21 during this period was checked and
indicated that there was no contribution due to the trial dredging
operation. Enhanced review of water quality around WCR2 was also
implemented and no deterioration in the water quality was observed.
4.4.20. Due to the access of water monitoring station at WSD19 was blocked
by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the inaccessibility
of sampling either land and marine, there is a fine adjustment of the sampling
point of WSD 19 since 5 April 2012 to the closest accessible point prior to the
completion of the construction activities.
4.4.21. Due to the dredging works for Cross Harbour Water Mains from
Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary
suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April
2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for
4-week period after the completion of DP6 to confirm no water deterioration.
4.4.22.
As
per the meeting with the representative of Excelsior Hotel and World Trade
Centre on 17 May 2011, they confirmed that the seawater intake for The
Excelsior was no longer in use and replaced by the connected permanent water
supply from WSD pipelines since 11 January 2011. Thus, the impact water quality
monitoring for the cooling intake - C6 was terminated effective from 26 May
2011.
4.4.23.
24 hours
monitoring of turbidity at the cooling water intakes at C7 was conducted. With respect to the seawall collapsing at TS4 on 17 November 2011, the
24 hours turbidity monitoring and was kept in November 2011. Since the
reinstating the seawall was completed on 13 January 2012 and no any water deterioration
was performed, 24 hour turbidity monitoring was then suspended on 27 January
2012.
4.4.24. Investigations were found that 6 turbidity and 5 SS
exceedances which were Project-related to Contract no. HK/2009/02 in October 2012. The details of the recorded exceedances can be referred to
the Section 5.4.
4.4.25.
The
enhanced water quality monitoring at C6, C7, Ex-WPCWA-SW and Ex-WPCWA-SE was
commenced on 13 January 2011. No
project-related exceedance was recorded in the daily SS monitoring and 24 hours
turbidity monitoring.
4.4.26.
Water
monitoring results measured in this reporting period are reviewed and
summarized in Table 4.16. Details of water quality
monitoring results and graphical presentation can be referred in Appendix 4.3.
Table 4.16 Summary of Water Quality Monitoring Exceedances in Reporting period
Contract
no. |
Water
Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished on 6 Feb 2012 |
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/01 |
WSD19 |
1 |
0 |
1 |
2 |
0 |
2 |
0 |
0 |
2 |
0 |
0 |
2 |
|
|
C1 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
2 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4e |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4w |
0 |
0 |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished on 27 April 2012 |
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
1 |
|
|
C5w |
0 |
0 |
1 |
0 |
1 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
|
Monitoring started on 8 Feb 2012 |
WSD21 |
0 |
1 |
0 |
2 |
0 |
2 |
1 |
0 |
0 |
1 |
1 |
1 |
|
WSD9 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/15 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/19 Monitoring started on 28 Jan 2012 |
C8 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
2 |
2 |
0 |
0 |
|
C9 |
0 |
0 |
3 |
1 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
Total |
4 |
1 |
8 |
8 |
7 |
4 |
1 |
0 |
6 |
4 |
1 |
4 |
||
Remarks: - The cessation of
seawater intake operation for C6 was confirmed on 17 May 2011, the water
monitoring at C6 was then terminated since 17 May 2011.
- WSD9 and
WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
- 4-week water quality monitoring at WSD9,
WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.
- C8 and C9 were implemented with respect to
HY/2009/19 from 28 Jan 2012.
-
WSD7 and WSD20 were temporarily suspended from 27 Apr 2012
4.4.27.
Enhanced
DO monitoring at 4 monitoring stations in Causeway Bay Typhoon Shelter and
Ex-Public Cargo Works Area was conducted three days per week during the
reporting period. The action and limit level exceedances of water quality
monitoring are summarized in Table 4.16a.
Table 4.16a
Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in
Reporting period
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
C7 |
2 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
1 |
4 |
0 |
2 |
|
Ex-WPCWA SE |
6 |
9 |
5 |
1 |
|
Total |
9 |
13 |
5 |
3 |
4.4.28.
There
was no exceedance in this reporting period are reviewed and summarized. Details of graphical presentation can be
referred in Appendix 4.3.
Contract no. HK/2009/01 - Wan Chai Development
Phase II – Central –Wanchai Bypass at HKCEC
4.5.1. No Inert C&D waste was
disposed and non-inert C&D
waste was disposed of for the site preparation works in this reporting period.
Details of the waste flow table are summarized in Table 4.18.
Table 4.18 Details of Waste Disposal for
Contract no. HK/2009/01
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
0 |
22245.415 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
0 |
5104.5 |
N/A |
Non-inert C&D materials disposed, m3 |
142.4 |
1234.48 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
0 |
151143 |
N/A |
Chemical waste disposed, kg |
750 |
9000 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal)
, m3 |
6264 (Bulk Volume) |
97428.2 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
8465 (Bulk Volume) |
52250 (Bulk Volume) |
East of Cha Chau |
Dredged Sediment Requiring Type 3 – Special Treatment / Disposal contained in
Geosynthetic Containers |
0 (Bulk Volume) |
6773 (Bulk Volume) |
East of Cha Chau |
Remarks: Contractor updated the quantity of Marine Sediment (Type 1 –
Open Sea Disposal) in February 2013.
4.5.2. There were Marine Sediment (Type 1 –
Open Sea Disposal) and Marine Sediment
(Type 1- Open Sea Disposal (Dedicate Sites) & Type 2- Confined Marine
Disposal) disposed of in this reporting quarter.
Contract no. HK/2009/02 - Wan Chai Development
Phase II – Central – Wan Chai Bypass at WanChai East
4.5.3. Inert and non-inert C&D waste were disposed of for the
site preparation works in this reporting period. Details of the waste flow
table are summarized in Table 4.19.
Table
4.19 Details of Waste Disposal for
Contract no. HK/2009/02
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
9965.05 |
229382.08 |
TKO137/ TM 38 |
Inert C&D materials recycled, m3 |
NIL |
18161 |
N/A |
Non-inert C&D materials disposed, m3 |
111.485 |
808.855 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Chemical waste disposed, kg |
350 |
6036 |
SENT Landfill |
Marine Sediment (Type 1 – Open Sea Disposal),
m3 |
NIL |
154,827 (Bulk volume) |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal), m3 |
2174 |
117420 (Bulk volume) |
East of Sha Chau |
Remarks:Contractor clarify the dumping of Type 1 – Open Sea Disposal
(Dedicate Sites) in December reporting month is 662 m3
4.5.4. There were Marine Sediment (Type 1- Open Sea
Disposal (Dedicate Sites) & Type 2- Confined Marine Disposal) disposed of
in this reporting quarter.
Contract no. HY/2009/15 -
Central-Wanchai Bypass – Tunnel (
4.5.5. No inert and non-inert C&D waste were disposed of for the site
preparation works in this reporting period. Details of the waste flow table are
summarized in Table 4.20.
Table
4.20 Details of Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
141579.2 |
Tuen Mun Area 38 |
NIL |
65216 |
TKO137 FB |
|
Inert C&D materials recycled, m3 |
NIL |
184.0 |
To Contract HY/2009/11 |
NIL |
304 |
Ex-PCWA |
|
|
NIL |
111.9 |
TS4 |
Non-inert C&D materials disposed, m3 |
NIL |
252.2 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
NIL |
299361.5 |
N/A |
Chemical waste disposed, kg |
NIL |
8,200 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal)
, m3 |
2351 |
100,208 (Bulk
Volume) |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
11,380 |
218,665 (Bulk
Volume) |
East of Sha Chau |
Marine Sediment (Type 3 – Special Treatment
/ Disposal contained in Geosynthetic Containers) |
0 |
7,050 (Bulk Volume) |
East of Sha Chau |
4.5.6. There was marine sediment (Type 1- Open Sea
Disposal) and Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites)
& Type 2 – Confined Marine Disposal) were disposed in this reporting quarter.
Contract
no. HK/2010/06 - Wan Chai Development Phase II – Central –Wanchai Bypass over
MTR Tsuen Wan Line
4.5.7. Non-inert C&D and Inert
C&D waste were disposed of
for the site preparation works in this reporting period. Details of the waste
flow table are summarized in Table 4.21.
Table
4.21 Details of Waste Disposal for
Contract no. HK/2010/06
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
0 |
11873 |
TM38 |
Inert C&D materials recycled, m3 |
0 |
267 |
N/A |
Non-inert C&D materials disposed, m3 |
0 |
50.15 |
N/A |
Non-inert C&D materials recycled, m3 |
0 |
60.58 |
N/A |
Chemical waste disposed, L |
0 |
2200 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal), m3 |
197 (Bulk Volume) |
3,891 (Bulk Volume) |
South Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
289 (Bulk Volume) |
(Bulk Volume) |
|
Remark: The Contractor updated the cumulative
quantity of disposed and recycled Inert C&D materials, disposed and
recycled Non-Inert C&D materials and chemical waste disposed in February
2013
4.5.8. There was marine sediment (Type 1- Open Sea
Disposal) and Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites)
& Type 2 – Confined Marine Disposal) were disposed in this reporting
quarter.
Contract
no. HY/2009/19 – Central- WanChai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link
4.5.9. Inert and non-inert C&D waste were disposed of
in this reporting quarter
Table
4.22 Details of Waste Disposal for Contract no.
HY/2009/19
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
60,323.69 |
153,914.93 |
TM38 |
Inert C&D materials recycled, m3 |
0 |
1323 |
N/A |
Non-inert C&D materials disposed, m3 |
106.83 |
258.36 |
N/A |
Non-inert C&D materials recycled, kg |
70.66 |
181.88 |
N/A |
Chemical waste disposed, L |
NIL |
0.29 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal), m3 |
83 |
83 |
South Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
182 |
664 |
|
Remark: After checking, the latest amount of
cumulative quantity-to-date of non-inert C&D materials disposed and
recycled have been updated.
4.5.10. There were marine sediments Type1- Open Sea
Disposal and Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 –
Confined Marine Disposal dredging from bore-piling casing in the reporting period.
5.0.1. The Event Action Plan for construction noise, air
quality and water quality are presented in Appendix 5.1.
4.1.8. Thirteen limit level exceedance was recorded at M6
on 29 November 2012, 11, 17 and 27 December 2012, 3, 8, 15, 24 and 29 January 2013, 7, 15, 19
and 26 February 2013 during this reporting quarter. Major traffic jam and no
major work activities were observed during monitoring, the exceedances were
considered as non-project related. Noise monitoring results measured in this
reporting period are reviewed and summarized.
Details of graphical presentation can be referred in Appendix 4.1.
5.2.2 Limit level exceedances were
recorded at RTN2a-Electric Centre during daytime on 31 Jan 2013 and during
restricted hours on 5, 11 and 12 Feb 2013. After checking with contractor, on
31 Jan 2013, no noisy construction activities were undertaken during the
recorded period. The exceedance was non-continuous and considered to be
contributed by the IEC traffic. On 11 and 12 Feb 2013, no construction
activities were conducted and the exceedances were considered to be contributed
by the Chinese New Year pyrotechnic display and IEC traffic respectively. As
such, the exceedances were concluded as non-project related. Appendix
4.2
5.3.1.
No
exceedance was recorded in 1-hr TSP and 24-hrs TSP monitoring in the reporting
period.
5.4.1.
The
summary of water quality exceedances recorded in reporting period is presented
in the Table 5.1 and Table 5.1a.
Table 5.1 Summary of Water Quality Monitoring Exceedances in
Reporting period
Contract
no. |
Water
Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished on 6 Feb 2012 |
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/01 |
WSD19 |
1 |
0 |
1 |
2 |
0 |
2 |
0 |
0 |
2 |
0 |
0 |
2 |
|
|
C1 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
2 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4e |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4w |
0 |
0 |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished on 27 April 2012 |
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
1 |
|
|
C5w |
0 |
0 |
1 |
0 |
1 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
|
Monitoring started on 8 Feb 2012 |
WSD21 |
0 |
1 |
0 |
2 |
0 |
2 |
1 |
0 |
0 |
1 |
1 |
1 |
|
WSD9 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/15 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/19 Monitoring started on 28 Jan 2012 |
C8 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
2 |
2 |
0 |
0 |
|
C9 |
0 |
0 |
3 |
1 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
Total |
4 |
1 |
8 |
8 |
7 |
4 |
1 |
0 |
6 |
4 |
1 |
4 |
||
Remarks: - The cessation of seawater intake operation
for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then
terminated since 17 May 2011.
- WSD9 and WSD17 were implemented with respect
to HK/2009/02 from 8 Feb 2012.
- 4-week
water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed
on 6 Feb 2012.
- C8 and C9 were implemented with respect to
HY/2009/19 from 28 Jan 2012.
- WSD7
and WSD20 were temporary suspended since 27 April 2012
5.4.2. All exceedances in Table 5.1 have been investigated
and there was no project-related exceedance.
Table 5.1a
Summary of Enhanced Dissolved Oxygen
Monitoring Exceedances in Reporting period
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
C7 |
2 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
1 |
4 |
0 |
2 |
|
Ex-WPCWA SE |
6 |
9 |
5 |
1 |
|
Total |
9 |
13 |
5 |
3 |
5.5.1. There was no non-compliance from the site audits in
the reporting period. During environmental site inspections conducted during
the reporting period, minor deficiencies were noted.
5.6.1 There was no non-compliance from
the site audits in the reporting period.
.
6.0.1. There was no complaint received in this reporting
period.
6.0.2.
The details of cumulative complaint
log and summary of complaints are presented in Appendix
6.1.
6.0.3. No notification of summons or prosecution was received in the reporting
period. Cumulative statistic
on complaints and successful prosecutions are summarized in Table
6.1 and Table 6.2 respectively.
Table 6.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works
(Mar 2010) to last reporting period |
27 |
Decemberr
2012- February 2013 |
0 |
Project-to-Date |
27 |
Table 6.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1. According
to Condition 3.4 of the EP-356/2009, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III, Central-Wanchai Bypass
and Island Eastern Corridor Link projects.
7.0.2.
According to the Monthly EM&A report (January
2013) of Central Reclamation Phase III (CRIII), filling works, road works,
landscape works, building construction works and drainage works were performed
in the February 2013 reporting month. The water quality monitoring was
completed in October 2011 and no project-related exceedance was
recorded for air and noise monitoring during the reporting quarter. It can be
concluded that cumulative construction impact due to the concurrent activities
of the current projects with the Central Reclamation Phase III (CRIII) was
insignificant
7.0.3. According
to the construction programme of Wan Chai Development Phase II, Central-Wan
Chai Bypass and Island Eastern Corridor Link projects, the major construction
activities at Reclamation Shoreline Sub-zones under Wan Chai Development Phase
II were the dredging and filling at HKCEC3w, dredging at submarine sewage
pipelines, reinstatement of seawall block construction at TCBR1W and marine
bored piling at MTR Tunnel Crossing in the reporting month. The major
environmental impact was water quality impact at North Point,
8.0.1. The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
8.0.2. No non-compliance was noted and no prosecution was
received during the reporting period.
8.0.3. The construction programmes
of individual contracts are provided in Appendix 7.1.